Tuesday, July 22, 2008 6:14 PM
From:
"John Chickness Sr"
To:
lakeashtontalk@yahoo.com
Core Samples are being completed on 72 selected sites in the Lake Ashton Community.
The process began on Monday AM and should be completed within 3 days.

These samples when completed will determine the structural soundness of the roads.

A typical Section of the construction of the road is:

1/12 inch of Asphalt , over 6 inches of Limerick Base ( LSB 100 ) over 8 inches of Stabilized Sub grade. ( FBV 60 ) A total road section is 15 1/2 inches in depth.

The samples of EACH boring/core samples are sent to a testing lab that will determine the soundness of the construction of the roads.

When the results are final...The CDD board of Supervisors will share the findings with the residents of Lake Ashton.

I have been on site during most of the core taking process. I found the firm to be very professional.

Respectfully

John L Chickness Sr CDD seat #4 Board of Supervisors , Lake Ashton 1 .




Core

Paul Pontious

Paul Pontious is the anonymous person that is criticising this web site. Please go and read your L A Times. Thanks to you your anonymous comments are too dirty to be published and your comments will no longer be accepted.

The Truth or not the truth

Why does Paul Pontious Tell the people Of Lake Ashton at the HOA meeting that all core samples were taken and they prove to me accepted, when in fact this was never true. Yet there are idiots out there that will criticize me for saying this. What do you want me to say, Paul is 100% right. I wish these people would go and read the L A Times and read about the good things that are going on here, nothing ever bad ever happens here. Get away from this web site and sit down with Joe Hunter and Paul Pontious. These guys never tell you the truth. Go and hear what these guys have to say. They are like the L A Times.